A $6.6 million Greene Street contract and a $5.4 million 15th Street contract go to committee Tuesday. Summit Construction was the low bidder on both.

Overview

Augusta commissioners will be asked Tuesday to award two road contracts worth about $12 million. One rebuilds Greene Street between 5th and 13th streets. The other covers 15th Street, starting at Government Road.

Summit Construction & Development LLC of Peachtree Corners, Georgia, was the low bidder on both. The Engineering Services Committee takes up the awards at 1:10 p.m. Tuesday, Nov. 24, in the Commission Chamber at 535 Telfair St. The contracts and bids are in the committee’s agenda packet (PDF).

Greene Street, 5th to 13th streets: $6.6 million

The Greene Street project is being built in two parts. Part 1, from 5th Street to East Boundary, is “substantially completed,” the city’s Engineering and Environmental Services Department wrote in the agenda item. Part 2 covers the blocks from 13th Street to 5th Street.

The department said Part 2 has been cut back “due to construction funds constraints.” It now covers:

  • new curb and gutter
  • the drainage work that goes with it
  • resurfacing

Summit bid $6,592,429.25. Federal funds cover $5,273,943.40 of that, and $1,318,485.85 comes from the city’s SPLOST 8 resurfacing money, according to the item. The federal share is part of an 80/20 cost-sharing arrangement. The award also depends on the Georgia Department of Transportation and Augusta signing a construction agreement for the project.

Four companies bid:

Bidder Bid
Summit Construction & Development LLC, Peachtree Corners $6,592,429.25
JHC Corporation, Newnan $7,989,732.10
E.R. Snell Contractor, Snellville $8,645,920.80
Reeves Construction Co., Augusta $9,649,286.00

15th Street: $5.4 million

The 15th Street job is a Transportation Investment Act project. It is on the list of projects area voters approved in the TIA referendum on June 9, 2020, the department said. The committee item calls it 15th Street from Government Road to Walton Way. The city’s bid invitation calls it 15th Street pedestrian improvements from Government Road to Laney Walker Boulevard.

The work includes:

  • resurfacing
  • rebuilding the existing curb and gutter
  • sidewalks
  • lighting
  • storm sewer improvements

The department said the project will improve roadway safety. Summit’s bid was $5,426,485.75: a base bid of $4,548,942.05 plus $877,543.70 for an alternate. The money comes from the project’s TIA funds.

Five companies bid. E.R. Snell came second at $5,701,812.37. Horizon Construction & Associates of Evans bid $6,046,478.85, Reeves Construction bid $6,138,948.95 and JHC Corporation bid $6,359,632.00.

More design money for Barton Chapel, Milledgeville and Highland

The same agenda adds design money for three south and west Augusta road projects. The design changes are “to enhance pedestrian use and improvement roadway aesthetics,” the supplemental agreements say.

Project Designer Added New design total
Barton Chapel Road, Deans Bridge Road to Augusta West Parkway Practical Design Partners $860,419 $1,540,406.18
Milledgeville Road, north leg to Barton Chapel Kimley-Horn $623,544 $1,208,734.51
Highland Avenue, Wrightsboro Road to Gordon Highway Kimley-Horn $400,000 $978,597.54

These are design contracts, not construction. The city held a public open house on the Barton Chapel and Milledgeville Road projects Nov. 12 but has not posted construction dates.

What it means for you

  • No start dates yet. Neither agenda item gives a construction start date or a detour plan. We will add them to our list of Augusta road closures when the city posts them.
  • Watch the committee. It meets at 1:10 p.m. Tuesday, Nov. 24, in the Commission Chamber, 535 Telfair St. The full Commission’s next meeting is listed for 2 p.m. Tuesday, Dec. 1.
  • Greene Street now: a separate streetlight job is keeping one lane of Greene Street closed between 5th Street and East Boundary until Dec. 16, according to the city’s Nov. 10 traffic advisory.