The Planning Commission hears the south Augusta data center rezoning at 2 p.m. Monday, Nov. 23. The state's regional review closed with a finding on Nov. 18.
Overview
The Augusta Planning Commission will hold a public hearing on the proposed south Augusta data center campus at 2 p.m. Monday, Nov. 23. The special called meeting is in the Augusta Commission Chambers, Room 260, on the second floor of the Municipal Building at 535 Telfair St.
The special called meeting agenda (PDF) lists only the data center. Anyone may attend and speak, and the city also takes comments by phone. The Planning Commission makes a recommendation. The Augusta Commission makes the final decision.
What is on the agenda
The applicant is 3 G Investments LLC, acting for The Nixon Trusts. Both requests cover about 383 acres at 1538 and 1550 Four H Club Road and 3806 Mike Padgett Highway, in District 1.
The agenda has two items:
- Z-26-18, a rezoning of the land from Agricultural, General Business and Heavy Industrial to a DC, or Data Center, zone
- SE-26-22, a special exception under Section 22-4(A) of the zoning ordinance to establish a data center
The rezoning request has changed. On the Nov. 2 Planning Commission agenda (PDF), the same case asked for Heavy Industrial zoning. That agenda shows both items “postponed until the December meeting by the Applicant.” The city then set the special called meeting for Nov. 23, according to its calendar notice.
Under the city’s data center ordinance (PDF), a data center campus is allowed only by special exception, and only with the Augusta Commission’s approval.
The state review is finished
The project is the Nixon Technology Center, which city planning staff filed with the state Oct. 12. Because of its size, it went through a state Development of Regional Impact review, run by the Central Savannah River Area Regional Commission.
The state’s Nixon Technology Center register page now lists the review as “Completed.” It records the regional commission’s finding on Nov. 18. The finding itself was not posted on the register or on the regional commission’s review page as of Thursday.
Under the state’s rules, the finding is advisory. It does not bind the city’s zoning decision.
The developer’s state filings describe a 3.34 million-square-foot campus. The second filing estimated a 600-megawatt peak electrical load, $3 billion in value, 40 full-time jobs and $38.8 million a year in local taxes. Our story on that filing has the full list. The filings gave the site as about 388 acres; the city’s agenda says about 383.
What it means for you
- Speak at the hearing. It starts at 2 p.m. Monday, Nov. 23, in Room 260 of the Municipal Building, 535 Telfair St.
- Can’t go? The agenda says written or verbal comments may be given to the Augusta Planning and Development Department at 706-821-1796 during regular business hours.
- Need an interpreter or an accommodation? Call the same number at least 48 hours before the meeting, the agenda says.
- The final vote comes later. The Augusta Commission decides after the Planning Commission’s recommendation. The city has not posted a date for that hearing.
- District 1 residents can reach their commissioner, Jordan Johnson, through the city contacts on our who to call at City Hall list.
Have your say